PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of new pedestrian bridge in village Chitakhevi, Borjomi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONApril, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

April, 2017

PROJECT NAMERehabilitation of Aspindza center square and Vardzia street blind alley, Aspindza municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of village Toki and Vargava motor roads (concrete) 2 stage, Aspindza municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of village Oti motor road, Aspindza municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation, asphalt works of village Ogora, Sakudabeli, Dzveli, Chobareti motor roads, Aspindza municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation (asphalt works) of village Iveria access road, Aspindza municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

May, 2018

PROJECT NAMERehabilitation of town Ninotsminda streets (Ketskhoveli, Pirosmani, Kirovi, Mikoiani, Chapaevi, Chavchavadze streets), Ninotsminda municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEVillage Jigrasheni road asphalt works, Ninotsminda municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEVillage Eshtia road asphalt works, Ninotsminda municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJuly, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

July, 2017

PROJECT NAMERehabilitation of the "big bridge" in town Borjomi, Borjomi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJuly, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

July, 2017