PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of Petre Bagrationi street in town Telavi, Telavi Municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

November, 2018

PROJECT NAMERehabilitation of Guramishvili street in town Telavi, Telavi Municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONJuly, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

July, 2018

PROJECT NAMERehabilitation of Lagidze street in town Telavi, Telavi Municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONJuly, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

July, 2018

PROJECT NAMERehabilitation of Paliashvili street in town Telavi, Telavi Municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONJuly, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

July, 2018

PROJECT NAMERehabilitation of the access road to village Matkhoji mother's monastery, Khoni municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONSeptember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

September, 2018

PROJECT NAMEContinuation of asphalt works on village Dedalauri road, Khoni municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONSeptember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

September, 2018

PROJECT NAMEAsphalt works from the main road to Barabadzeebi district in village Matkhoji, Khoni municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONSeptember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

September, 2018

PROJECT NAMERehabilitation of the road connecting Kapnari-Kelasouri in village Marelisi, Kharagauli municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

December, 2018

PROJECT NAMERehabilitation of village Uchmeti road, Kharagauli municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONSeptember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

September, 2018

PROJECT NAMERehabilitation of village Lashe (Zeda Lashe) road, Kharagauli municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONSeptember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

September, 2018