PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEConstruction of nursery school for borough Mestia, Mestia municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEConstruction of kindergarten for Becho (Mazeri), Mestia municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEConstruction of kindergarten for Mulakhi (in Chola), Mestia municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEConstruction of Khaishi kindergarten, Mestia municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEConstruction of Idliani kindergarten, Mestia municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEVillages Kurzu and Dgvani part connection road arrangement with concrete cover, Martvili municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEVillage Gurdzemi road rehabilitation with asphalt-concrete cover, Martvili municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEVillages KIhuntsi and Nagvazao connection road rehabilitation with asphalt-concrete cover (second stage), Martvili municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEVillages Salkhino and Tsachkhura part connection road rehabilitation with asphalt-concrete cover (third stage), Martvili municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of motor road in Darcheli administrative unit, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017