PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of village Sulda administrative building (village house, children entertainment center), Akhalkalaki municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONAugust, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

August, 2018

PROJECT NAMERehabilitation of villages Toki and Vargava access roads, III stage, Aspindza municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

June, 2018

PROJECT NAMERehabilitation of borough Aspindza internal streets: I and II blind alleys of Chavchavadze street, blind alleys of Tabidze, Marjanishvili, Gogebashvili and Gorgasali streets, Aspindza Municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

June, 2018

PROJECT NAMERehabilitation of village Imertubani-Ijareti connection road, Adigeni Municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

June, 2018

PROJECT NAMERehabilitation of Sakvikvino road (arrangement of cement concrete cover) in 1 May administrative unit, Khobi municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

December, 2018

PROJECT NAMEAmenities of streets and improvement of infrastructure in village Khobi, Khobi municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

May, 2018

PROJECT NAMEAmenities of borough center that includes rehabilitation of drainage canals, multi-storey residential building yards, traffic lights and squares, Chkhorotsku municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONJuly, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

July, 2018

PROJECT NAMERehabilitation of the road connecting villages Akhuti and Noga, Chkhorotsku municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONSeptember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

September, 2018

PROJECT NAMEArrangement of asphalt-concrete cover on Sarodonaio and Saarakhamio district road sections, Chkhorotsku municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

June, 2018

PROJECT NAMEArrangement of asphalt-concrete cover on Rustaveli district road in village Lesichine, Chkhorotsku municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

June, 2018