PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of I.Chavchavadze and Tbilisi streets in Darcheli administrative unit, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

May, 2018

PROJECT NAMERehabilitation of motor road from Narazeni central road to Opachkhapu center in Opachkhapu administrative unit, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONApril, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

April, 2018

PROJECT NAMERehabilitation of motor road from Oktomberi center through former professional school and Akhalkakhati (to Zugdidi-Anaklia motor road) in Oktomberi administrative unit, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

November, 2018

PROJECT NAMERehabilitation of motor road in Natsatu administrative unit from Zugdidi- Tsalenjikha central road towards Natsatu to the border of Tsalenjikha municipality, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

November, 2018

PROJECT NAMERehabilitation of Tkaia administrative unit central motor road, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONApril, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

April, 2018

PROJECT NAMERehabilitation of motor road connecting Koki - Orsantia (III stage), Zugdidi municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

May, 2018

PROJECT NAMERehabilitation of #2 kindergarten in town Tsageri, Tsageri municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

December, 2018

PROJECT NAMEAsphalt works in town Tsageri, Tsageri municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

November, 2018

PROJECT NAMEArrangement of bridge crossing in Manavi, Sagarejo municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

November, 2018

PROJECT NAMEArrangement of drainage canal in village Zemo Mackhaani, Dedoplistskaro municipality
START OF CONSTRUCTIONMarch, 2018
END OF CONSTRUCTIONJuly, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Category

Drainage systems

Construction schedule

START OF CONSTRUCTION

March, 2018

End of construction

July, 2018