PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of motor road in October administrative unit from October center through the former professional school and Akhalkakhati (to Zugdidi-Anaklia motor road), Zugdidi municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

October, 2017

PROJECT NAMERehabilitation of the road section (Tsereteli street) connecting the center of the Akhalabastuni administrative unit, Zugdidi municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

September, 2017

PROJECT NAMEArrangement of water supply network in Kulishkari administrative unit, Zugdidi municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMEArrangement of asphalt-concrete cover on the road from village Marani to village Tkhmelari, Abasha municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

September, 2017

PROJECT NAMERehabilitation works of village Shardometi access road section damaged by the landslide, Oni municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

October, 2017

PROJECT NAMEArrangement of sewerage network in village Gari, Oni municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

June, 2018

PROJECT NAMEAmenities of square on King Tamar street, J. Meshveliani park, central square and heroes memorial, Lentekhi municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMEArrangement works of tourism facilities, springs amenities and sports-recreation square, Ambrolauri municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONAugust, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Category

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

August, 2018

PROJECT NAMECement-concrete surfaced motor road arrangement works for Bostana, Ambrolauri municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMERehabilitation - construction of road infrastructure, Mtskheta city municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Category

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017