PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of 4.8km roads in Sagandzili administrative unit villages (village Vani 3760m, village Chkheri 1000m), Kharagauli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMEAmenities of Chavchavadze street #9 and #11 and Dedaena street #11 and #13 apartment yards, Tskaltubo municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

October, 2017

PROJECT NAMERehabilitation of Ninoshvili №5,1 blind alleys, to Besiki street №5,7,9 apartments, road to Shanidze №10 apartment, Dadiani and 26 May streets №2 blind alley, roads to Tsereteli №1, 9 April №1, №1a, №5 apartments, road connecting 9 April №3 and Kostava s
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

September, 2017

PROJECT NAMERehabilitation of the roads in Tskaltubo town Evdoshvili and Khandzteli street connection section, Samakashvili, Tsitlanadze streets, Village Khomuli (White cave) and village Maglaki (Imereti supporting point), Tskaltubo municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

August, 2017

PROJECT NAMERepair entrances in town Kutaisi, Kutaisi City Municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMEArrangement of concrete slabs on Meskhishvili street I and III turning in town Kutaisi, Kutaisi City Municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

October, 2017

PROJECT NAMEArrangement of asphalt-concrete cover on Lagidze, Vakhushti, Old Samtredia, Old Samtredia II blind alley, Gagarini, 9May, Gogodze, Agmashenebeli III blind alley, Tsinsvla streets and road from Tsinsvla street to 7th public school, Samtredia municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMERehabilitation of kindergarten in village Basileti, Chokhatauri municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Guria

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMEConstruction of kindergarten in village Bukistsikhe, Chokhatauri municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Guria

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of old administrative building in village Vani in order to allocate library and youth center and completion of rehabilitation of former administrative building damaged by the fire in village Goraberejouli, Chokhatauri municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Guria

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017