PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of district road in village Dziroki, Gurjaani municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMEArrangement of asphalt-concrete cover on Tbilisi street in town Akhmeta, Akhmeta municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMEArrangement of asphalt-concrete cover on Kvareli street in town Akhmeta, Akhmeta municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMEArrangement of reinforced concrete stormwater canals in village Duisi, Akhmeta municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Category

Drainage systems

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMEConstruction of the building for emergency medical service in town Khoni, Khoni municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMERehabilitation of village Sakarikedi motor road (200m), Kharagauli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

October, 2017

PROJECT NAMERehabilitation of the road connection Legvani-Marelisi (4600m), Kharagauli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of the central road of village Lakhundara (Lower Lakhundara, church district) (2350 m), Kharagauli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

October, 2017

PROJECT NAMERehabilitation of the central road of village Legvni (4076 m), Kharagauli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of the streets and the blind alleys, cleaning of canals in borough Kharagauli, Kharagauli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017