PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEIn village Asureti restoration recovery of XIX century German architectural church, and residential houses on Stalin street and cemetery, Tetritskaro municipality
START OF CONSTRUCTIONJuly, 2017
END OF CONSTRUCTIONJuly, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kvemo Kartli

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

July, 2017

End of construction

July, 2018

PROJECT NAMERehabilitation of Water Supply Network; Abasha
START OF CONSTRUCTIONJuly, 2017
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Bidding

Construction schedule

START OF CONSTRUCTION

July, 2017

End of construction

December, 2018

PROJECT NAMEAsphalt works on Eladi street in town Kvareli, Kvareli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

September, 2017

PROJECT NAMEAsphalt works on "Mirinaant: district in village Shilda, Kvareli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

August, 2017

PROJECT NAMEAsphalt works on Ilia Chavchavadze street I blind alley in town Kvareli, Kvareli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

September, 2017

PROJECT NAMEAsphalt works on Baratashvili street in town Kvareli, Kvareli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

September, 2017

PROJECT NAMEAsphalt works on Sulkhan-Saba street (from Gogebashvili street to Ilia hill) in town Kvareli, Kvareli municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

August, 2017

PROJECT NAMERehabilitation of Arsenishvili street, Town Telavi municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

September, 2017

PROJECT NAMERehabilitation of 9 April street (square in front of the police)road cover in town Tsnori, Signagi municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

August, 2017

PROJECT NAMERehabilitation of Rustaveli street (beginning) road cover in town Tsnori, Signagi municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

August, 2017