PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERetaining wall arrangement in village Akhaldaba, Tbilisi
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONJuly, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Tbilisi

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

July, 2017

PROJECT NAMERehabilitation of #1 kindergarten in Tsalenjikha, Tsalenjikha municipality
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONFebruary, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

February, 2018

PROJECT NAMEDusheti park rehabilitation, Dusheti municipality
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

May, 2018

PROJECT NAMERehabilitation of Tskneti-Samadlo and Tskneti-Akhaldaba road damaged due to disaster of June 13, 2015 (design/ construction), Tbilisi
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Tbilisi

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

May, 2018

PROJECT NAMEClosure of the existing landfill, Lanchkhuti
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONJune, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Guria

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

June, 2017

PROJECT NAMERehabilitation (asphalt works) of village Iveria access road, Aspindza municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

May, 2018

PROJECT NAMEConstruction of the bridge connecting villages Tushurebi - Jervalidzeebi, Tianeti municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

October, 2017

PROJECT NAMERehabilitation of water supply system in villages: Zurabebi, Doreulebi and Vedzatkheva, Tianeti municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

November, 2017

PROJECT NAMEArrangement of mini stadiums on Priest Tevdore and 9 April streets, Khashuri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJuly, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Tbilisi

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

July, 2017

PROJECT NAMEAsphalt works on Zemo Khvedureti - Kheoba - Chandrebi road, Kareli municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017