PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of damaged bridge crossing section located in the entrance of village Gvedi on 37th km of Kutaisi-Tskaltubo-Tsageri-Lentekhi-Lasdili motor road, Khoni municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

August, 2017

PROJECT NAMERehbilitation of 3 and 5 storey residential building facades (Freedom square #12;13;15; Solomon II street #7), Khoni municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

September, 2017

PROJECT NAMERehabilitation of Art School in town Khoni, Khoni municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

August, 2017

PROJECT NAMERehabilitation of study of local lore museum of Khoni, Khoni municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

August, 2017

PROJECT NAMERehabilitation of village Golatubani central road (500m section), Kharagauli municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

November, 2017

PROJECT NAMERehabilitation of Nebodziri road, Kharagauli municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of village Vakhani central road , Kharagauli municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of 1km central road in Moliti administrative unit village Kvebi, Kharagauli municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of 1900m roads in Tskalporeti administrative unit villages (village Khoni 400m, village Lakhundara 1500m), Kharagauli municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of the building for kindergarten in village Nadaburi, Kharagauli municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

October, 2017