PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEArrangement of asphalt-concrete on the road from the end of Akaki street to village Kodori, Abasha municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

October, 2017

PROJECT NAMEArrangement of asphalt-concrete on the road from Sagvazao school to village Dziguri, Abasha municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

October, 2017

PROJECT NAMEAsphalt works on village Zudali-Shkmeri road, Oni municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

August, 2017

PROJECT NAMERehabilitation of water supply system in village Utsera, Oni municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

November, 2017

PROJECT NAMECement-concrete surfaced motor road arrangement works in village Chkvishi, Ambrolauri municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

September, 2017

PROJECT NAMECement-concrete surfaced motor road arrangement works in village Dzirageuli, Ambrolauri municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

September, 2017

PROJECT NAMECement-concrete surface arrangement works on central motor road in village II Tola, Ambrolauri municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

September, 2017

PROJECT NAMECement-concrete surfaced motor road arrangement works in village Sadmeli, Ambrolauri municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

September, 2017

PROJECT NAMECheliagele-Tlugi cement-concrete surfaced motor road arrangement works, Ambrolauri municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

September, 2017

PROJECT NAMESecondary works to arrange water supply system for village Bugeuli, Ambrolauri municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

November, 2017