PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEFootball stadium construction, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMEMineral water Amenities, Oni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of Lesemi and Lemzagori-Kheria bridges, arrangement of Bondi bridge in Rtskhmeuluri and two pedestrian bridges, Lentekhi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMEAsphalt works of borough streets and amenities of Chavchavadze street, Lentekhi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMEAmenities of L Museliani museum and Tvilbedi branch (storages, showcases, Jargvali amenities), Lentekhi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMEConstruction of club in villages Tekali and Mele, construction of a youth center in the villages Sasa and Kheledi, Lentekhi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMEUpper and Lower Panagi, Mami-Ukleshi and Sakdarui water, Lentekhi municipality rehabilitation
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMEConstruction of Gvimbrali garden and outpatient building in Rtskhmeula garden , Lentekhi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMEArrangement of 18 mini stadiums, Lentekhi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMEAmenities of square on King Tamar street, J. Meshveliani park, municipality yard and heroes memorial on central square, Lentekhi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017