PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEArrangement works for tourist facilities and springs amenities, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMECheliagele-Tlugi cement-concrete surfaced motor road arrangement works, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation works on Ambrolauri-Khimshi motor road, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMESecondary works - rehabilitation of Krikhi-Ambrolauri motor road, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of water headwork, main line and internal network of village Kldisubani, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMESecondary works to arrange water supply system for village Bugeuli, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of Viktor Fitskhelauri street in borough Stefantsminda. Road to access hotel Rooms, Kazbegi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of Ilia Chavchavadze street in borough Stefantsminda, Kazbegi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of the road connecting Tserovani-Chardakhi, Mtskheta municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of internal roads in village Mukhrani, Mtskheta municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2017