PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEAmenities of Maltakva coastline (including access road), Poti municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

October, 2018

PROJECT NAMERehabilitation of facades of buildings and structures, Zugdidi municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

August, 2017

PROJECT NAMEVillages Khuntsi and Nagvazao connection road rehabilitation with asphalt-concrete cover (second stage), Martvili municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

November, 2017

PROJECT NAMEVillages Salkhino and Tsachkhura part connection road rehabilitation with asphalt-concrete cover (third stage), Martvili municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

August, 2017

PROJECT NAMERehabilitation of motor road in Abastumani administrative unit (second stage), Zugdidi municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

September, 2017

PROJECT NAMERehabilitation of motor road in Chkhori administrative unit, Zugdidi municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONJuly, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Category

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

July, 2017

PROJECT NAMEArrangement of asphalt-concrete on the road from Gezati center to school, Abasha municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

October, 2017

PROJECT NAMEArrangement of asphalt-concrete cover on the road from village Matskhovriskari to village Dzveli Abasha, Abasha municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

October, 2017

PROJECT NAMEArrangement of asphalt-concrete on the road from Ninoshvili 1st turning to Ioseliani street connection, Abasha municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

October, 2017

PROJECT NAMEArrangement of asphalt-concrete on Aleksandre Abasheli street, Abasha municipality
START OF CONSTRUCTIONJune, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2017

End of construction

October, 2017