PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of 1,5km road in Khevi administrative unit village Tsaqva, Kharagauli municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

October, 2017

PROJECT NAMEKopitebi Nigozeti motor road restoration, Chiatura municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJuly, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

July, 2017

PROJECT NAMESachkhere highway- Zodi motor road restoration, Chiatura municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJune, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

June, 2017

PROJECT NAMEKvatsikhe highway-Jvarieweri motor road restoration, Chiatura municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJuly, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

July, 2017

PROJECT NAMEKvatsikhe highway-Vachevi motor road restoration, Chiatura municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJune, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

June, 2017

PROJECT NAMEMemoriali-Rgani Khreiti motor road restoration, Chiatura municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJuly, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

July, 2017

PROJECT NAMERehabilitation of the roads from villages Kvitiri and Brotseula to Tskaltubo town Tbilisi street №5 apartment, Tskaltubo municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJuly, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

July, 2017

PROJECT NAMERehabilitation of the roads in Tskaltubo town Gvantseladze, Gamsakhurdia, Akhalgazrdoba, Lortkipanidze 7th turning and village Sakulia, Tskaltubo municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEArrangement of concrete cover on the road together with storm-water gutters in town Kutaisi K. Gamsakhuridia street (from clinical hospital to rugby base), Kutaisi City Municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEArrangement of sidewalks on Akhalgazrdoba avenue, Kutaisi City Municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017