PROJECT NAMERehabilitation of village Ojio water supply system, Akhmeta municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

October, 2017

PROJECT NAMEAsphalt works on 800m road in village Gocha-Jikhaishi from middle school to the temple, Khoni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEAsphalt works on the road in village Kontuati from main road to the center of Kontuati, Khoni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEAsphalt works in village Kukhi from central road to school, Khoni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEAsphalt works of Pushkini street road to 4th district cemetery in town Khoni, Khoni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEAsphalt works of Gogebashvili street in town Khoni, Khoni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEAsphalt works of Gorgasali street extension in town Khoni, Khoni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEAsphalt works of p. Kakabadze street in town Khoni , Khoni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEAsphalt works of G. Chanturia street turnings in town Khoni (behind the post office and entering Tutisani street), Khoni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMEAsphalt works of D. Kakabadze street in town Khoni, Khoni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction