PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEArrangement of drainage canal in village Zemo Machkhaani, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Category

Drainage systems

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMERehabilitation of the existing footbridge on Dumbadze street in village Khornabuji, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEArrangement of square and children entertainment attractions in yards nearby the multi-apartment residential buildings on Hereti street #2a in town Dedoplistskaro, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEArrangement of asphalt cover on the roads to the buildings located on Rustaveli street in town Dedoplistskaro, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEArrangement of asphalt cover on the 2nd street of village Samreklo, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMERehabilitation of asphalt on Tsereteli street in town Dedoplistskaro, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEArrangement of asphalt cover and cuvettes on Samkhedro street in town Dedoplistskaro, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEArrangement of asphalt cover on Paliashvili and Sarajishvili streets in town Dedoplistskaro, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMERehabilitation of asphalt cover on Evdoshvili and Lomi streets in town Dedoplistskaro, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEArrangement of concrete cover on "Vanchukaant" district road in village Bakurtsikhe, Gurjaani municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017