PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEAsphalt works on "I.Gogebashvili" street in town Kvareli, Kvareli municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEAsphalt works on Ilia Chavchavadze and Racha street 1200m section and rehabilitation of drainage channels in town Kvareli, Kvareli municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAME26 May street rehabilitation (with turnings) - asphalt works with the arrangement of side-walks and drainages in town Telavi, Telavi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEElene akhvlediani street rehabilitation (with turnings) - asphalt works with the arrangement of side-walks and drainages in town Telavi, Telavi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEApril street rehabilitation (with turnings) - asphalt works with the arrangement of side-walks in town Telavi, Telavi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of "Gvinobaatnt" district road in village Anagi, Signagi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of Freedom street in Tsnori town, Signagi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of internal district roads in village Kvemo Magaro, Signagi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEConstruction of kindergarten in village Bodbiskhevi, Signagi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERepair works of kindergarten in village Ninotsminda, Sagarejo municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017