PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEReconstruction-rehabilitation works on sports complex building in town Oni, Oni municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2018

PROJECT NAMEArrangement of cultural, sports and educational center building in village Chrebalo, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

October, 2017

PROJECT NAMERehabilitation works on Ambrolauri-Khimshi motor road, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMESecondary works - rehabilitation of Krikhi-Ambrolauri motor road, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

August, 2017

PROJECT NAMERehabilitation of water headwork, main line and internal network of village Kldisubani, Ambrolauri municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEFull rehabilitation of Merab Kostava street in borough Stefantsminda, Kazbegi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2018

PROJECT NAMEFull rehabilitation of Shota Rustaveli street in borough Stefantsminda, Kazbegi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

November, 2017

PROJECT NAMEFull rehabilitation of Viktor Fitskhelauri street in borough Stefantsminda. Road to access hotel Rooms, Kazbegi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

November, 2017

PROJECT NAMEFull rehabilitation of Ilia Chavchavadze street in borough Stefantsminda, Kazbegi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

December, 2018

PROJECT NAMERehabilitation-Construction of road infrastructure, Mtskheta city municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

October, 2017