PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEArrangement of Tourist Infrastructure and Urgent Restoration Works for Zarzma Monastery, Adigeni municipality
START OF CONSTRUCTIONMay, 2019
END OF CONSTRUCTIONNovember, 2020
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

May, 2019

End of construction

November, 2020

PROJECT NAMERehabilitation works for access road to Vani archeological museum, Vani municipality
START OF CONSTRUCTIONMay, 2019
END OF CONSTRUCTIONNovember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Region

Imereti

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

May, 2019

End of construction

November, 2019

PROJECT NAMERehabilitation of km24+620-km50+244 of Moliti-Chumateleti Road (LOT II)
START OF CONSTRUCTIONMay, 2019
END OF CONSTRUCTIONMay, 2021
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Shida Kartli

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

May, 2019

End of construction

May, 2021

PROJECT NAMERehabilitation of Aghobili Hotel -LTD access road, and arrangement of power supply system and internet infrastructure, Adigeni municipality
START OF CONSTRUCTIONMay, 2019
END OF CONSTRUCTIONSeptember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

May, 2019

End of construction

September, 2019

PROJECT NAMERehabilitation of two access earth- roads for hotel Mgzavrebi Gudauri and internet infrastructure arrangement, Dushetis municipality
START OF CONSTRUCTIONMay, 2019
END OF CONSTRUCTIONSeptember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

May, 2019

End of construction

September, 2019

PROJECT NAMERehabilitation of river Achkvi bed, Kobuleti Municipality
START OF CONSTRUCTIONJune, 2019
END OF CONSTRUCTIONSeptember, 2020
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Region

Adjara

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

June, 2019

End of construction

September, 2020

PROJECT NAMEArrangement of tourist infrastructure in Gudauri, Kazbegi municipality
START OF CONSTRUCTIONJune, 2019
END OF CONSTRUCTIONJune, 2020
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

June, 2019

End of construction

June, 2020

PROJECT NAMEConstruction of Waste Water Treatment Plant; Abastumani
START OF CONSTRUCTIONJune, 2019
END OF CONSTRUCTIONDecember, 2021
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Construction schedule

START OF CONSTRUCTION

June, 2019

End of construction

December, 2021

PROJECT NAMERehabilitation of Sewerage Network; Abastumani
START OF CONSTRUCTIONJune, 2019
END OF CONSTRUCTIONDecember, 2021
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Construction schedule

START OF CONSTRUCTION

June, 2019

End of construction

December, 2021

PROJECT NAMEConstruction of Khevi-Ubisa section of E-60 Highway (F2)
START OF CONSTRUCTIONJune, 2019
END OF CONSTRUCTIONJune, 2022
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

June, 2019

End of construction

June, 2022