PROJECT NAMERehabilitation of Terenti Graneli culture and leisure park, Tsalenjikha municipality
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

December, 2018

PROJECT NAMERehabilitation of multi-apartment residential building roofs yards, Poti municipality
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

December, 2018

PROJECT NAMEArrangement of sewerage network in Akhaldasakhleba district of Kveda Tsageri, Tsageri municipality
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

December, 2018

PROJECT NAMEArrangement of sewerage network in town Ambrolauri, Ambrolauri municipality
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

December, 2018

PROJECT NAMERehabilitation of km0+000-km24+620 of Dzirula-Moliti Road Section (LOT I)
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONJuly, 2020
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

July, 2020

PROJECT NAMERehabilitation of Kintsvisi-Gverdzineti-Tkemlovana Road in Dzama Gorge, Kareli Municipality
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONSeptember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Shida Kartli

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

September, 2019

PROJECT NAMERehabilitation of Toba-Varchkhili Vehicle Road, Chkhorotsku Municipality
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONSeptember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

September, 2019

PROJECT NAMEConstruction works for water supply and wastewater systems of "Gino Wellness Group" recreational complex in village Bakuriani, Borjomi municipality
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONOctober, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

October, 2019

PROJECT NAMEConstruction of Waste Water Treatment Plant; Agara
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONJune, 2020
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Shida Kartli

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

June, 2020

PROJECT NAMEConstruction of Sewerage Network; Agara
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONJune, 2020
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Shida Kartli

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

June, 2020