PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of childrens football school building, Lanchkhuti municipality
START OF CONSTRUCTIONAugust, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Guria

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2018

End of construction

December, 2018

PROJECT NAMEArrangement of R/C stormwater channels, R/C and asphalt concrete cover in Aketi, Atsana, Chibati, Ninoshvili, Nigvziani, Mamati and Supsa administrative units, Lanchkhuti municipality
START OF CONSTRUCTIONAugust, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Guria

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2018

End of construction

December, 2018

PROJECT NAMERehabilitation of Mothers Monastery access road in Jikheti, Lanchkhuti municipality
START OF CONSTRUCTIONAugust, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Guria

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2018

End of construction

December, 2018

PROJECT NAMEVillage Eshtia road rehabilitation, Ninotsminda municipality
START OF CONSTRUCTIONAugust, 2018
END OF CONSTRUCTIONFebruary, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

August, 2018

End of construction

February, 2019

PROJECT NAMERehabilitation and design of Mziuri Park in Tbilisi City, Tbilisi
START OF CONSTRUCTIONAugust, 2018
END OF CONSTRUCTIONJanuary, 2020
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Tbilisi

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

August, 2018

End of construction

January, 2020

PROJECT NAMERehabilitation of Brosteula Settlement Road in Village Martkopi, Gardabani Municipality
START OF CONSTRUCTIONAugust, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Kvemo Kartli

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

August, 2018

End of construction

December, 2018

PROJECT NAMERehabilitation of motor road from village Khvani turning to village Lichi center, Sachkhere municipality
START OF CONSTRUCTIONAugust, 2018
END OF CONSTRUCTIONAugust, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Imereti

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

August, 2018

End of construction

August, 2019

PROJECT NAMEConstruction of Waste Water Treatment Plant; Marneuli
START OF CONSTRUCTIONAugust, 2018
END OF CONSTRUCTIONDecember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Bidding

Region

Kvemo Kartli

Construction schedule

START OF CONSTRUCTION

August, 2018

End of construction

December, 2019

PROJECT NAMERehabilitation of N6 and N10 multi apartment building access roads with concrete cover, Tskaltubo Municipality
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Imereti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

October, 2018

PROJECT NAMERehabilitation of Terenti Graneli culture and leisure park, Tsalenjikha municipality
START OF CONSTRUCTIONSeptember, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2018

End of construction

December, 2018