PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of an access road to village Kushi, Tsalka Municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONJuly, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kvemo Kartli

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

July, 2018

PROJECT NAMERehabilitation of Water Supply Network; Kulbaki (Tsageri +15 Villages)
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONDecember, 2020
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

December, 2020

PROJECT NAMERehabilitation of access road to Zedazeni monastery, arrangement of parking area and access path to the church, Mtskheta municipality
START OF CONSTRUCTIONJuly, 2018
END OF CONSTRUCTIONMay, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

July, 2018

End of construction

May, 2019

PROJECT NAMEConstructuin of emergency situations coordination and urgent assistance center office in town Abasha, Abasha municipality
START OF CONSTRUCTIONJuly, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

July, 2018

End of construction

December, 2018

PROJECT NAMEArrangement of asphalt cover on Vazha-Pshavelan street in village Khornabuji, Dedoplistskaro municipality
START OF CONSTRUCTIONJuly, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

July, 2018

End of construction

October, 2018

PROJECT NAMEArrangement of asphalt cover on Vazha-Pshavelan street in town Dedoplistskaro, Dedoplistskaro municipality
START OF CONSTRUCTIONJuly, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

July, 2018

End of construction

October, 2018

PROJECT NAMERehabilitation of asphalt cover on Leonidze street in town Dedoplistskaro, Dedoplistskaro municipality
START OF CONSTRUCTIONJuly, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

July, 2018

End of construction

October, 2018

PROJECT NAMERehabilitation of km14.6-km25.8 section of Tchrebalo-Nikortsminda Road
START OF CONSTRUCTIONJuly, 2018
END OF CONSTRUCTIONJuly, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

July, 2018

End of construction

July, 2019

PROJECT NAMERehabilitation of Tsalenjikha-Nakipu-Letsurtsume-Chkhorotsku Road, Tsalenjikha Municipality
START OF CONSTRUCTIONJuly, 2018
END OF CONSTRUCTIONMarch, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

July, 2018

End of construction

March, 2019

PROJECT NAMERehabilitation of Likani and Tsagveri Water Supply Systems Phase 2, Borjomi municipality
START OF CONSTRUCTIONJuly, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

July, 2018

End of construction

December, 2018