PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEConstruction of Waste Water Treatment Plant; Gudauri
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONNovember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Bidding

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

November, 2019

PROJECT NAMERehabilitation of Abastumani Observatory infrastructure, Adigeni municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONSeptember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

September, 2019

PROJECT NAMERehabilitation of the cemetery access road in Guripuldi administrative unit village Pirveli Guripuldi, Khobi municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

December, 2018

PROJECT NAMEConstruction of kindergarten in village Lataki, Mestia municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONFebruary, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

February, 2019

PROJECT NAMEReconstruction-rehabilitation of chess school building, Zugdidi municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

December, 2018

PROJECT NAMEArrangement of asphalt-concrete on the road from Gezati center to school, Abasha municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

October, 2018

PROJECT NAMEArrangement of asphalt-concrete cover on the road from village Matskhovriskari to village Dzveli Abasha, Abasha municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

October, 2018

PROJECT NAMEArrangement of asphalt-concrete on the road from Ninoshvili 1st turning to Ioseliani street connection, Abasha municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

October, 2018

PROJECT NAMEArrangement of asphalt-concrete on Tsanava street road (from Gas bureau to Liberty street), Abasha municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

October, 2018

PROJECT NAMEArrangement of asphalt-concrete on Gamsakhurdia street IV turning road, Abasha municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

October, 2018