PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of central motor road in Chkhori administrative unit (first stage), Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of central motor road in Tkai administrative unit (third stage), Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of water supply network in Kulishkari administrative unit (second stage), Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMEArrangement of the bridge in Kortskheli administrative unit connecting to village Chkaduashi, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of road connecting Koki-Orsantia (second stage), Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of internal motor road in Kakhati administrative unit (Rustaveli street) first stage, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of motor road in Grigolishi administrative unit (from Grigolishi center to Zugdidi-Kulishkari motor road (second stage)), Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of central motor road in Akhalabastumani administrative unit (second stage), Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of water supply network in Abastumani administrative unit, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of water supply network in Upper Etseri administrative unit, Zugdidi municipality
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

December, 2017