PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of central motor road in Chkhoria administrative unit (II stage), Zugdidi municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

December, 2018

PROJECT NAMERehabilitation of the road connecting to the center (Tsereteli street) in Akhalabastumani administrative unit, Zugdidi municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

December, 2018

PROJECT NAMEN2 kindergarten construction, Zugdidi municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONJune, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

June, 2019

PROJECT NAMERehabilitation of Tsaishi and Tsatskhvi administrative unit (resort section) motor road, Zugdidi municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

May, 2018

PROJECT NAMERehabilitation of Didinedzi Kakhati administrative unit motor road (second stage), Zugdidi municipality
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

October, 2018

PROJECT NAMEConstruction of Waste Water Treatment Plant; Poti
START OF CONSTRUCTIONApril, 2018
END OF CONSTRUCTIONDecember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Bidding

Construction schedule

START OF CONSTRUCTION

April, 2018

End of construction

December, 2019

PROJECT NAMEExternal lightning of parks, squares and centers, Tsalenjikha municipality
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

November, 2018

PROJECT NAMEAmenities of central street sidewalks (King Parnavaz street, from samegrelo square to Rustaveli circle), Poti municipality
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

December, 2018

PROJECT NAMEArrangement of asphalt-concrete cover on St. Barbare temple access road in village Najakhao, Martvili municipality
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONAugust, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

August, 2018

PROJECT NAMEArrangement of concrete cover on the motor road of small Inchkhuri district in village Inchkhuri , Martvili municipality
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONAugust, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

August, 2018