PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of culture house (second stage), Tsalenjikha municipality
START OF CONSTRUCTIONMay, 2016
END OF CONSTRUCTIONMay, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2016

End of construction

May, 2017

PROJECT NAMEConstruction of #4 and Chkvaleri kindergartens (second stage of Mikava and Jagali kindergartens), Tsalenjikha municipality
START OF CONSTRUCTIONMay, 2016
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2016

End of construction

December, 2018

PROJECT NAMESecond stage works of cultural-educational and youth center creation, Khobi municipality
START OF CONSTRUCTIONJune, 2016
END OF CONSTRUCTIONJanuary, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2016

End of construction

January, 2018

PROJECT NAMERehabilitation of 1km section of Abasha-Gagma Kodori-Guleiskiri-Japana road
START OF CONSTRUCTIONFebruary, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

February, 2017

End of construction

September, 2017

PROJECT NAMEArrangement of the bridge in Kortskheli administrative unit connecting to village Chkaduashi, Zugdidi municipality
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

August, 2017

PROJECT NAMERehabilitation of existed tunnel on km 59 road section of Zugdidi-Jvari-Mestia-Lasdili
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONAugust, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

August, 2018

PROJECT NAMEWorks to be implemented for safety of water protection structures and traffic on 2,4 km of Abasha-Martvili road
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of #1 kindergarten in Tsalenjikha, Tsalenjikha municipality
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

May, 2018

PROJECT NAMEStreet amenity works (cement concrete) on Sachokairo district of 1st May administrative unit, Khobi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

November, 2017

PROJECT NAMEStreet amenities and infrastructure improvement, Khobi municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017