PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEArrangement of asphalt cover on the road from village Mereti to village Zariaantkari, Gori municipality
START OF CONSTRUCTIONJune, 2013
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2013

End of construction

August, 2017

PROJECT NAMESports complex construction in Khashuri, Khashuri municipality
START OF CONSTRUCTIONApril, 2016
END OF CONSTRUCTIONApril, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

April, 2016

End of construction

April, 2018

PROJECT NAMELightening works on Ruisi-Agara E-60 highway
START OF CONSTRUCTIONMarch, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

March, 2017

End of construction

November, 2017

PROJECT NAMERehabilitation of a bridge crossing on km 13 of Igoeti-Kaspi-Akhalkalaki road
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONAugust, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

August, 2017

PROJECT NAMERehabilitation of 1 km road section of Khashuri-Akhaltsikhe-Vale (Border of Turkey)
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

October, 2017

PROJECT NAMEAsphalt works on Zemo Khvedureti - Kheoba - Chandrebi road, Kareli municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEAsphalt works on Mokhisi-Kodavardisubani local significance road, Kareli municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMERehabilitation of Tengiz Burjanadze football stadium, Town Gori municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONJune, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

June, 2017

PROJECT NAMERehabilitation of art school exterior, Town Gori municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

September, 2017

PROJECT NAMEAsphalt works on I.Gogebashvili II and III blind alley, #17 kindergarten access road adjacent to Shindisi highway, Gorgasali and Khakhutashvili connection, Chavchavadze blind alley and connection from Rustaveli to Khashuri street, Town Gori municipality
START OF CONSTRUCTIONMay, 2017
END OF CONSTRUCTIONOctober, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Shida Kartli

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2017

End of construction

October, 2017