PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEAsphalt works on cemetery road and on the entrances from central road to district roads, Gurjaani municipality
START OF CONSTRUCTIONAugust, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2018

End of construction

December, 2018

PROJECT NAMEArrangement of necessary infrastructure, boreholes, access road and power supply for Ltd "Jiveli", Telavi municipality
START OF CONSTRUCTIONOctober, 2018
END OF CONSTRUCTIONJune, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Kakheti

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

October, 2018

End of construction

June, 2019

PROJECT NAMEConstruction of Sagarejo-Bakurtsikhe road section
START OF CONSTRUCTIONFebruary, 2019
END OF CONSTRUCTIONFebruary, 2021
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Region

Kakheti

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

February, 2019

End of construction

February, 2021

PROJECT NAMEConstruction of Tbilisi-Sagarejo road section
START OF CONSTRUCTIONFebruary, 2019
END OF CONSTRUCTIONFebruary, 2021
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Region

Kakheti

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

February, 2019

End of construction

February, 2021

PROJECT NAMEConstruction of Bakurtsikhe-Tsnori road section
START OF CONSTRUCTIONMarch, 2019
END OF CONSTRUCTIONMarch, 2021
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Region

Kakheti

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

March, 2019

End of construction

March, 2021

PROJECT NAMEArrangement of water borehole for vine company Kardanakhi 1888 in Gurjaani municipality, Gurjaani municipality
START OF CONSTRUCTIONApril, 2019
END OF CONSTRUCTIONJune, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Region

Kakheti

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2019

End of construction

June, 2019

PROJECT NAMERehabilitation of the Megobrebis Wine Cellar - JSC access road, and arrangement of internet infrastructure, Kvareli Municipality
START OF CONSTRUCTIONApril, 2019
END OF CONSTRUCTIONJune, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Region

Kakheti

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2019

End of construction

June, 2019

PROJECT NAMEConstruction of new regional landfill, Closure of existing landfills, Kakheti and Samegrelo-Zemo Svaneti
START OF CONSTRUCTIONApril, 2021
END OF CONSTRUCTIONNovember, 2021
PROJECT STATUS/CONSTRUCTION COMMENCEMENT

Region

Kakheti

Construction schedule

START OF CONSTRUCTION

April, 2021

End of construction

November, 2021