PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of pedestrian road to access dendrology park and amenities of park, Signagi municipality
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

November, 2018

PROJECT NAMERehabilitation of kindergarten building in village Arkhiloskalo, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

December, 2018

PROJECT NAMEArrangement-rehabilitation of potable water internal network in village Arboshiki, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

November, 2018

PROJECT NAMERehabilitation of potable water main line network in village Zemo Kedi, Dedoplistskaro municipality
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONSeptember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

September, 2018

PROJECT NAMEAsphalt works on village Bakurtsikhe internal road (Samadaant district), Gurjaani municipality
START OF CONSTRUCTIONMay, 2018
END OF CONSTRUCTIONSeptember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

May, 2018

End of construction

September, 2018

PROJECT NAMEMetering of potable water network in village Sabue, Kvareli municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONDecember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

December, 2018

PROJECT NAMEArrangement of potable water network in village Kakabeti, Sagarejo municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONOctober, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

October, 2018

PROJECT NAMERehabilitation of kindergarten motor road in village Iliatsminda, Signagi municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

November, 2018

PROJECT NAMERehabilitation of "Garajebi" district motor road in village Jugaani, Signagi municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

November, 2018

PROJECT NAMERehabilitation of cemetery motor road in village Dzveli Anagari, Signagi municipality
START OF CONSTRUCTIONJune, 2018
END OF CONSTRUCTIONNovember, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

June, 2018

End of construction

November, 2018