PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMEArrangement of asphalt cover on M. Gelovani street in village Khornabuji, Dedoplistskaro municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

June, 2018

PROJECT NAMEArrangement of asphalt cover and rehabilitation of the footbridge on M. Kostava street in village Khornabuji, Dedoplistskaro municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

June, 2018

PROJECT NAMEArrangement of external lights on local significance roads in town Dedoplistskaro, Dedoplistskaro municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Category

Accomplishment

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMERehabilitation of district road in village Dziroki, Gurjaani municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMEArrangement of asphalt-concrete cover on Tbilisi street in town Akhmeta, Akhmeta municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMEArrangement of asphalt-concrete cover on Kvareli street in town Akhmeta, Akhmeta municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMEArrangement of reinforced concrete stormwater canals in village Duisi, Akhmeta municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Category

Drainage systems

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMEArrangement of artificial surfaced sport stadiums in town Tsnori, village Nukriani (threshing-floors) old Anagi and Kvemo Machkhaani, rehabilitation in village Kvemo Bodbe, Signagi municipality
START OF CONSTRUCTIONSeptember, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of "Gvinobaatnt" district road in village Anagi (second stage), Signagi municipality
START OF CONSTRUCTIONSeptember, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2017

End of construction

November, 2017

PROJECT NAMERehabilitation of the access road to #2 kindergarten in village Gurjaani (II stage), Gurjaani municipality
START OF CONSTRUCTIONSeptember, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2017

End of construction

December, 2017