PROJECT NAMEArrangement of asphalt-concrete cover on Kvareli street in town Akhmeta, Akhmeta municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

December, 2017

PROJECT NAMEArrangement of reinforced concrete stormwater canals in village Duisi, Akhmeta municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Category

Drainage systems

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

November, 2017

PROJECT NAMEArrangement of artificial surfaced sport stadiums in town Tsnori, village Nukriani (threshing-floors) old Anagi and Kvemo Machkhaani, rehabilitation in village Kvemo Bodbe, Signagi municipality
START OF CONSTRUCTIONSeptember, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2017

End of construction

November, 2017

PROJECT NAMERehabilitation of "Gvinobaatnt" district road in village Anagi (second stage), Signagi municipality
START OF CONSTRUCTIONSeptember, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2017

End of construction

November, 2017

PROJECT NAMERehabilitation of the access road to #2 kindergarten in village Gurjaani (II stage), Gurjaani municipality
START OF CONSTRUCTIONSeptember, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2017

End of construction

December, 2017

PROJECT NAMERehabilitation of 1200m road in Lashi administrative unit village Khvemali and rehabilitation of the road in Manjavidzeebi district (250m to Boris Manjavidze house), Kharagauli municipality
START OF CONSTRUCTIONSeptember, 2017
END OF CONSTRUCTIONDecember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

September, 2017

End of construction

December, 2017

PROJECT NAMEArrangement of external underground communication networks for multifunctional sports complex under construction adjacent to Alazani avenue in town Telavi, Town Telavi municipality
START OF CONSTRUCTIONOctober, 2017
END OF CONSTRUCTIONNovember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

October, 2017

End of construction

November, 2017

PROJECT NAMEAmenity works on stadium area in town Sagarejo, Sagarejo municipality
START OF CONSTRUCTIONOctober, 2017
END OF CONSTRUCTIONJanuary, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Kakheti

Implementing authority

Municipality

Construction schedule

START OF CONSTRUCTION

October, 2017

End of construction

January, 2018

PROJECT NAMEArrangement of water borehole for vine company Kardanakhi 1888 in Gurjaani municipality, Gurjaani municipality
START OF CONSTRUCTIONOctober, 2017
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

October, 2017

End of construction

June, 2018

PROJECT NAMEArrangement of necessary infrastructure, boreholes, access road and power supply for Ltd "Jiveli", Telavi municipality
START OF CONSTRUCTIONOctober, 2017
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Kakheti

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

October, 2017

End of construction

June, 2018