PROJECTS 2017-2020

Information uploaded on the web-page applies to the projects planned through 2017 – 2020 and may be corrected without prior notification

DOWNLOAD FILE:

PROJECT NAME
START OF CONSTRUCTION
END OF CONSTRUCTION
PROJECT STATUS/CONSTRUCTION COMMENCEMENT
PROJECT NAMERehabilitation of bridge crossing at km130 of Batumi-Akhaltsikhe road
START OF CONSTRUCTIONApril, 2017
END OF CONSTRUCTIONSeptember, 2017
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Completed

Region

Adjara

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

April, 2017

End of construction

September, 2017

PROJECT NAMETown Kobuleti - Coastline protecting structure rehabilitation subproject, Kobuleti municipality
START OF CONSTRUCTIONAugust, 2017
END OF CONSTRUCTIONJune, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Adjara

Implementing authority

Municipal Development Fund of Georgia

Construction schedule

START OF CONSTRUCTION

August, 2017

End of construction

June, 2018

PROJECT NAMEConstruction of Batumi bypass section of E-70 highway
START OF CONSTRUCTIONNovember, 2017
END OF CONSTRUCTIONMay, 2020
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Ongoing

Region

Adjara

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

November, 2017

End of construction

May, 2020

PROJECT NAMELightening works on Kobuleti bypass road section E-70 (LOT I)
START OF CONSTRUCTIONDecember, 2017
END OF CONSTRUCTIONMay, 2018
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2017

Region

Adjara

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

December, 2017

End of construction

May, 2018

PROJECT NAMEConstruction of Goderdzi-Zarzma road section (LOT II)
START OF CONSTRUCTIONJanuary, 2018
END OF CONSTRUCTIONNovember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Adjara

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

January, 2018

End of construction

November, 2019

PROJECT NAMEConstruction of Khulo-Goderdzi road section (LOT I)
START OF CONSTRUCTIONJanuary, 2018
END OF CONSTRUCTIONNovember, 2019
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2018

Region

Adjara

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

January, 2018

End of construction

November, 2019

PROJECT NAMEConstruction of E-70 Batumi -Sarpi road section
START OF CONSTRUCTIONFebruary, 2019
END OF CONSTRUCTIONJuly, 2021
PROJECT STATUS/CONSTRUCTION COMMENCEMENT Construction Commencement: 2019

Region

Adjara

Implementing authority

Roads Department of Georgia

Construction schedule

START OF CONSTRUCTION

February, 2019

End of construction

July, 2021